Inertia worked with Weyers Develpments and WG Architects on both the civil and structural engineering of these 9 new townhouses in Coorparoo. Three of these involved renovating and building underneath existing residences, while the remaining five are new three storey constructions.

Inertia is also responsible for the construction management and supervision of this development, which is currently in construction. There was up to 2m of fill that had to be brought on to the project site to achieve levels above the flooding issues. Because of this the existing houses had to be suspended on steel columns and bream framed with about 5m clearance from the natural ground level to the underneath of the  timber floor of the existing structure whilst the fill was compacted underneath.

 