Back to Projects

Wattle Grove, Cannon Hill

Inertia partnered with Lennium Group for the engineering design and construction of this 40 unit boutique townhouse development in Cannon Hill. The development presented a number of engineering challenges such as a sloping block requiring multiple retaining walls and the development of stormwater treatment devices.

The project also faced challenging Council Conditions outside of our scope, including but not limited to; high-risk fauna management, development of a major construction management plan, and arboricultural and vegetation management plans. To support our client and other project partners with managing these Conditions our team developed a Development Approval (DA) matrix. The matrix outlined the requirements, deliverables and timeframes for each condition making coordination and submission as smooth as possible.

We are happy to report that the OPW approval encountered no Requests For Information (RFI) which expedited the approval process.

In the Construction phase, we provided construction coordination between the developer, the builder and local authorities through pre-start meeting and routine site inspections as well as any changes in design required to suit the existing site conditions.

Our DA matrix was also instrumental in ensuring a smooth transition from the construction stage to final plan sealing and turn key dates.

 

Completion2018

DescriptionTownhouse Development

ClientLennium Group

CategoryHousing